Data contoh.
Rencana PM
| Work Center | Sub-sistem | Sistem | Line | Interval | Estimasi (j) | Toleransi (hari) | Item checklist | Jatuh tempo berikutnya | WO PM 30 hari | Status |
|---|---|---|---|---|---|---|---|---|---|---|
| MEC 1 | RK3-DS Drive System | Rotary Kiln 3 | Production Line 3 | 1 bulan | 6,0 | 3 | 3 Ukur, 2 Periksa | 26 Nov 2026 | 1 | Aktif |
| MEC 1 | RK3-DS Drive System | Rotary Kiln 3 | Production Line 3 | 6 bulan | 16,0 | 7 | 5 Ukur, 3 Periksa | 2 Mar 2027 | 0 | Aktif |
| MEC 1 | RK3-RK Rotary Kiln | Rotary Kiln 3 | Production Line 3 | 2 minggu | 4,0 | 2 | 2 Ukur, 4 Periksa | 23 Nov 2026 | 2 | Aktif |
| MEC 1 | RK1-OME Ore Mixing Equipment | Rotary Kiln 1 | Production Line 1 & 2 | 14 hari | 1,5 | 1 | 1 Ukur, 3 Periksa | 1 Des 2026 | 1 | Aktif |
| MEC 1 | RD1-DS Drive System | Rotary Dryer 1 | Production Line 1 & 2 | 1 bulan | 8,0 | 3 | 4 Ukur, 2 Periksa | – | 0 | Nonaktif |
| ELE 1 | RK3-DS Drive System | Rotary Kiln 3 | Production Line 3 | 1 bulan | 3,0 | 3 | 4 Ukur, 1 Periksa | 4 Des 2026 | 1 | Aktif |
| ELE 1 | RK1-DS Drive System | Rotary Kiln 1 | Production Line 1 & 2 | 3 bulan | 5,0 | 5 | 6 Ukur, 2 Periksa | 15 Jan 2027 | 0 | Aktif |
| ELE 1 | RD1-PS Power Supply | Rotary Dryer 1 | Production Line 1 & 2 | 1 minggu | 1,25 | 0 | 0 Ukur, 5 Periksa | 24 Nov 2026 | 1 | Aktif |